Stephens Road Bridge Project

August 25, 2025

Stephens Road Bridge  Replacement Project 

This project is being managed by the Warren County Engineer’s Office.

Project Scope:

Bridge #158-0.92 is in need of replacement as the existing concrete box beams are deteriorating. The bridge will be replaced with a new precast concrete box culvert type bridge. The bridge is located on Stephens Road, over a branch of Bear Run, between Hargus Drive and Village Green Parkway in Hamilton Township.

Traffic Impacts:

Stephens Road at the bridge will be closed for the entire length of the project, utilizing the following detour: SR 48, US 22/SR 3, and Zoar Road.

Project Schedule:

Construction will begin on Monday, September 15, 2025 and is expected to have a duration of twelve (12) weeks, weather permitting.

Construction Cost:

The project construction was awarded to JTM Smith Construction for $539,516.47, and will be funded by Federal funds through the County Engineer’s Association of Ohio and the Warren County Engineer’s Office.

Stephens Road Bridge Replacement